Tower base hole as specificed will be 4ft x 4ft x 5ft deep. 1st 6 inches is gravel and sand for moisture drainage, followed by 4 cement blocks that hold the bottom rebar grid up into the poured concrete. Tower base legs stick down into the gravel/sand (below the concrete so as to drain any water that may form in the tower legs. Another rebar grid will be embedded in the poured concrete 42 inches above the bottom grid seen in the picture.